Project Update – November 2, 2026
- Last Week Kays Contracting completed the watermain works, including the final watermain tie-in at Delany Ave/Harold St. The Ward Avenue intersection was reopened, and Kays started sub-excavation for road gravels. Additional fencing was installed prior to Halloween weekend, to support the construction site safety and open cut areas adjacent to walking.
- This Week, Kays will continue with sub-excavation work along Harold Street. They intend to leave the NW corner of the site at current grade, to allow for access to the three businesses at the north end. They will begin importing sub base course aggregates following sub-excavation work, and intend to get a proof roll done on Tuesday, November 3rd. Kays will then start installing shallow utilities (electrical), including street light bases.
- Looking ahead, Kays is tentatively planning to install curb and gutter during the week of November 16th, and to pave the week of November 23rd. This is very weather dependent, and temperatures are being monitored daily. If temperatures and weather are unfavourable, paving will be postponed until spring. Regardless, the road will be repoened to regular traffic and parking during the winter.
|